Replacement of PO UN02 Carga at Górka Cement Plant in Trzebinia

HLI was invited to execute a project at the Górka Cement facility in Trzebinia. Our challenge was to comprehensively design and supply a system for the replacement of the kiln ring along with the sub-ring carga of a rotary kiln. The experienced HLI team ensured smooth execution of the operation, and the transport system prepared for this task performed flawlessly, enabling the safe and seamless movement of the 35-ton ring with its carga.

Scope of Work

  • Component weight: 35 tons,
  • Lifting height: 5 m
  • Design of the installation concept,
  • Design, supply, and installation of temporary structures,
  • Supply of Strand Jacking technology and other hydraulic systems for horizontal adjustments of the transported element,
  • Supply of modular structural systems,
  • Comprehensive horizontal and vertical transport services.