Lifting of HRSG Pressure Components – Infraserv Höchst

HLI was invited to participate in coordinating the heavy lifting operations for the construction of two HRSG boilers, each weighing 1050 tonnes. The boiler components were transported from the prefabrication yard to the assembly site using SPMT (Self-Propelled Modular Transporters). Our scope included coordination of all the heaviest transports using SPMTs and both hydraulic and lattice cranes to their final positions. Additionally, HLI was responsible for the direct installation of the supplied strand jack system used for lifting the pressure sections of the boilers (800 tonnes each) and providing essential assistance during all lifting operations.

Scope of Works

  • Collaboration with multiple stakeholders, leveraging HLI personnel experience in strand jack lifting operations.
  • General support for client personnel during assembly works.
  • Installation and operation of the strand jack system and other specialized lifting equipment.
  • Supervision and coordination of horizontal and vertical transport of oversized elements,
  • Direct supervision of third-party personnel.